AISB · Verified CRE Claims Library

Verified CRE Claims: Project Management

US/Singapore-weighted reference corpus — curated and verified by AISB's knowledge engine; not exhaustive.

This library is an informational reference, not engineering or legal advice. Confirm the current edition of any cited standard with the issuing body before relying on it for design, compliance, or investment decisions.

Owner-side capital projects: earned value, scheduling, permits, and AACE practice.

8 verified claims · back to the library hub

The DCMA 14-point schedule assessment sets a threshold that positive lags (delays inserted between predecessor and successor activities) should appear on no more than 5% of all schedule relationships.

Durable standard Source: AACE Internationalverified 2026-07-02

Under AACE International Recommended Practice 18R-97, a Class 5 cost estimate (concept screening, 0-2% project definition) carries an expected accuracy range of -50% to +100%.

Durable standard Source: AACE Internationalverified 2026-07-02

The DCMA 14-point schedule assessment sets a threshold of zero tolerance for negative float in a CPM schedule, since negative float signals a hard-constraint-driven delay to project or milestone completion.

Durable standard Source: AACE Internationalverified 2026-07-02

Under AACE RP 18R-97, approximately 80% of projects are expected to fall within their stated estimate-class accuracy range when contingency has been addressed appropriately (an 80% confidence interval convention).

Durable standard Source: AACE Internationalverified 2026-07-02

The DCMA 14-point schedule assessment sets a threshold that no more than 5% of a CPM schedule's total incomplete task duration should carry total float exceeding 44 working days (the 'high float' check).

Durable standard Source: AACE Internationalverified 2026-07-02

The DCMA 14-point schedule assessment sets a threshold of 0% tolerance for negative lag (leads) in a CPM schedule, since leads distort the network and make forward/backward-pass float calculations unreliable.

Durable standard Source: AACE Internationalverified 2026-07-02

The DCMA 14-point schedule assessment requires that no more than 5% of schedule activities have missing predecessor or successor logic ties (excluding the project start and finish milestones).

Durable standard Source: AACE Internationalverified 2026-07-02

The DCMA 14-point schedule assessment requires that at least 90% of all activity relationships in a CPM schedule be Finish-to-Start (FS) logic ties for the schedule to pass this quality check.

Durable standard Source: AACE Internationalverified 2026-07-02
Generated 2026-07-03 by AISB's deterministic claims-library generator from the verified knowledge corpus. Each claim carries its source anchor and admission class. US/Singapore-weighted reference corpus — curated and verified by AISB's knowledge engine; not exhaustive.